Project delivery case study
Distribution centre fit-out
on time and within budget
Global chemicals manufacturer
Project management on the client side for a new distribution centre in North Yorkshire, from contractors and CDM 2015 duties to stock migration and go-live.
£15m
Programme value
280,000 sq ft
Site size
15+
Contractors coordinated
20,000+
SKUs migrated
The challenge
Consolidating three sites into one
A global chemicals manufacturer was moving three legacy sites into a new 280,000 sq ft distribution centre in North Yorkshire, with two office fit-outs of 20,000 sq ft each.
The legacy sites had to keep running until go-live, so the move of stock and systems was planned around live operations.
Delivery was led on the client side for phase one, a £15m programme run within the client’s established capital governance.
What made it complex
- Three legacy sites running until go-live
- 15+ contractors working on one site
- A go-live date that had to be held
- Every change within capital governance
What was delivered
Warehouse project management from fit-out to go-live
One delivery lead across contractors, budget, safety, systems and stock.
Contractor coordination
15+ contractors across mechanical, electrical, HVAC, racking, security, fire suppression, civils and two office fit-outs, run to one programme.
Budget and change control
Scope changes and costs managed within the client’s capital governance, alongside finance, procurement and stakeholders.
Health and safety
Site lead under CDM 2015, working with the Principal Contractor on inspections, contractor activity and commissioning approval.
Systems readiness
SAP integration supported and user acceptance testing coordinated with the operation, so systems were ready for go-live.
Stock migration
Migration of 20,000+ SKUs from three legacy sites overseen, with inventory and operations kept running throughout the move.
Handover
Commissioning approved, then the new distribution centre handed to the operation at go-live on time and within budget.

The result
Delivered on time and within budget, with 20,000+ SKUs moved into the new distribution centre without a break in operations.
35,000+
Racking locations
20+
Dock doors
60+
Peak site headcount
Related services
Service used
New sites, fit-outs, relocations and go-lives run as one programme, from early scoping through to handover.
Run alongside
New systems, processes and sites introduced with training and adoption planned in, so the change holds.
Where to start
An independent review with a written action plan showing the causes and what to fix, for a fixed £2,450.
Planning a fit-out, relocation or new site?
Describe the project and get a clear view of how it could be delivered, from contractors and budget to handover.
Or reach out directly
Phone
Discuss your project
Send a few details and we will be in touch to discuss.